We spoke with our SS today to find out if we would have an opportunity to walk through and discuss the position of the light switches and apparently our pre-lining walk through will be toward the end of next week. He also gave a rundown of the plan for the next few weeks and it sounds action packed. Bricks are due to finish next Monday, carpenters start Tuesday, plumbing on Wednesday and a brick clean should also happen. Gyprocking will then start around Tuesday 11th Feb. It's all happening!